The Supply Point can contain the following values:

  • Nominated KVA
  • Physical kVA
  • TRIAD Demand
  • EAC Values



To add these:

Open the Estate Management Activity

  • Click on the Supply Point Tab
    • Highlight the Supply Point
  • Click Edit Supply Point

         


The Supply Point Editor popup appears:

  • Click on Nominated kVA, Physical kVA or TRIAD Demand 
    • Click Edit Data
    • Click Actions > Add Reading > At start
    • Amend the Date to the date you want the value to start
    • Click OK to open the HFD Data Viewer popup
    • Double click into Value field and add the required value 

                   

    • Click OK to save

                           