The Network Charge Validation is carried out in the USM (Utility Specific Module) within the EDI Supplier Setup Activity. Click here for more information:
This page explains the terminology used in Network Charge Validation
The LLF (Line Loss Factor) is he distance from a grid connection point and is the 3rd part of the top line of the MPAN
Distribution Losses is the difference between the electricity entering the distribution network and that leaving it (i.e. going into a meter).
It is the first part of the core MPAN and the ID of the distributor for the area the MPAN is in.
The ASC (Agreed Supply Capacity) in the bill below, it is called the DUoS Availability .
Paying for the privilege of a maximum available supply capacity (ASC) from the grid at any one time (p/kVA/day).
A penalty charge which is levied if a Supply consumes more than its allotted ASC within a given period (p/kVA/day as per the excess capacity used)
The difference between the electricity supplied and amount of power that can be used (p/kVArh)