The cost of any exception found (overspend or shortfall) can be optionally calculated.
Opening the Reporting Activity
Open Sigma and click on Reporting
Running the Report
Choose the Site, Meter, Channel or Monitoring Point that you want to run the Report on
...
Click to run the Report at specific times (see below)
Scheduling the Report
Create the Report as above (don't click on Run Report)
...
Enter the Name
Enter a Description
Click Next to go to the Report Configuration screen
These details are the same as entered on the Report - do not amend
Click Next to go to the Report Output screen
...
Tick how you want to receive the Report
Click Next to go to the Report Date screen
Choose Dynamically set the date to 1 Day 2 Days before execution time so that the Report will always use the day before
This will take you to the last whole day, so running the report at 03:00 on 27th will give you the data for all of 26th
Click Next to go to the Fixed end date screen
Choose Dynamically set the date to 1 Day before execution time so that the Report will always use the day before
Click Next to go to the Activation screen
...
Choose the date and time you want the Report to run (choose the time to reflect the time of day you want to run the report, ie best practice is overnight)
Note: If you are running the report overnight, you will need to ensure that data is in Sigma prior to the Report Run Time.
Click Next to go to the Recurrence screen
Choose the recurrence, for example Daily
Click Next to go to the Run time(s) screen
...
Enter a figure in the Select number of days, ie 1
Click Next to go to the Schedule End screen
Choose never, after or on
Click OK to save
The Report is now scheduled and will either send a Report each day if All channels has been ticked
...